MOQ, lead time and container fill: planning a mixed order that pays for its freight
How this guide was written: every figure below is either taken from a published standard named in the sentence, or read from the specification of an item in our own catalogue. Where a number is an industry rule of thumb rather than a standard, the text says so. No customer names, certificate numbers or inspection results are quoted unless they come from an order file.
Short answer: plan a mixed tool order around the container’s two limits, because only one of them will bind. A 40 ft high cube holds about 76 m³ but only about 26 tonnes of payload; steel tools hit the weight limit while gloves, PPE and packaging hit the volume limit — so the cheapest container is the one that carries a weight-dense line and a volume-dense line together. Then check the MOQ arithmetic before the fill arithmetic: an MOQ of 1,000 pieces per size across 12 sizes is a 12,000-piece commitment, and that number is what decides whether the order fits at all.
This guide gives the capacity figures, the weight-versus-volume logic, the MOQ questions that change the answer, and a planning sequence that gets a mixed order to a booked vessel without air freight at the end.
The figures to plan with
- 20 ft: about 33 m³, payload roughly 28 t.
- 40 ft: about 67 m³, payload roughly 26.5 t.
- 40 ft high cube: about 76 m³, payload roughly 26 t.
- Pallet counts: roughly ten to eleven EUR pallets (1200 × 800 mm) in a 20 ft and twenty to twenty-one in a 40 ft, single tier — confirm with a loading plan, because pallet overhang and door width change the count.
- Weight or volume: steel tools are weight-limited, gloves and PPE are volume-limited. Mixed orders should contain both.
- Lead time: 25–35 days production for catalogue items, 45–60 days with new tooling, plus 5–7 days for booking and a 2–4 week shutdown around Chinese New Year.
1. Container capacity: the limit that actually binds
| Container | Internal volume | Payload (approx.) | EUR pallets, single tier | Typically binds on |
|---|---|---|---|---|
| 20 ft standard | ≈ 33 m³ | ≈ 28 t | 10–11 | Weight for steel, volume for light goods |
| 40 ft standard | ≈ 67 m³ | ≈ 26.5 t | 20–21 | Volume, unless the load is dense |
| 40 ft high cube | ≈ 76 m³ | ≈ 26 t | 20–21 (42 double-stacked, light goods) | Volume for bulky items; weight for tools |
Note the counter-intuitive part: the 40 ft carries more volume but less weight than a 20 ft, because the container’s own weight is higher while the road limit is the same. Loading a 40 ft to its cubic capacity with dense steel tools will put you overweight long before it is full, and the terminal will not load it.
2. Weight against volume: what your mix should look like
Every product has a stowage factor — cubic metres per tonne. Container dimensions and ratings are standardised (ISO 668 series) and the industry-level constraints are summarised by the World Shipping Council. Dense goods have a low figure, light goods a high one. Hand tools, wrenches, sockets and casters are dense; gloves, helmets, empty cases and packaging are light. A container of only dense goods reaches 26 t at maybe half its volume; a container of only light goods fills up at a fraction of the payload.
The practical planning rule: for every pallet of dense steel, plan roughly two to three pallets of light volume goods. That way both limits are approached at about the same time, and the freight per unit lands near its minimum. If you are shipping a single category, price the two options honestly — sometimes a 20 ft of steel plus LCL for the light items is cheaper than a part-full 40 ft.
3. The MOQ arithmetic, before anything else
MOQ is quoted in three different ways and the difference is expensive:
- Per order: 5,000 pieces total, any mix. The most flexible and the one to ask for first.
- Per item: 1,000 pieces of each article number. Twelve sizes becomes 12,000 pieces.
- Per colour or per size: 500 pieces per colour of each size, which multiplied across a range is how a tidy order becomes four pallets of one size.
Then there is the tooling question. A new die, a printed carton or a custom colour adds a one-off cost that only amortises over volume. If the MOQ is being driven by a print run, ask what the price is with a plain carton — the answer often moves the MOQ down by half and is the single most useful question in mixed-order planning.
4. Lead time, and the two dates that ruin plans
Catalogue items typically run 25–35 days from deposit to ready-to-ship; items with new tooling 45–60 days. Add 5–7 days for booking and documentation, and the sea transit. Two calendar events break schedules more than anything else:
- Chinese New Year. Factories close for two to four weeks and ramp up slowly afterwards. An order placed six weeks before the holiday frequently ships six weeks after it. Place CNY-adjacent orders at least 90 days ahead, or accept air freight on the shortfall.
- Peak season booking. Space tightens and rates rise before major Western retail seasons. Booking a mixed container three weeks out in peak season means paying spot rates.
Both are predictable, and both are cheaper to plan for than to recover from.
5. The planning sequence that works
- Fix the list and the quantities per article. Not per category — per article number, because that is what MOQ is measured against.
- Ask for MOQ per order and per item, separately. Write both numbers down; they are different commercial offers.
- Estimate carton dimensions and weights per article. Suppliers have these; if they do not, ask for one carton to be measured and photographed.
- Calculate total volume and total weight. If weight binds first, you are short of light goods; if volume binds first, you are short of dense goods.
- Re-balance the mix rather than paying for air freight on the overflow. The re-balance is usually a substitution inside the same category, not a new supplier.
- Confirm the production schedule in writing with a ready date, and book against that date plus a week.
- Inspect before shipment, not on arrival — a pre-shipment inspection at AQL is far cheaper than a claim after the container has sailed. What an inspection scope covers is described by firms such as Intertek.
6. Where the fill actually comes from in a tool order
Dense lines to anchor the weight: wrenches, socket sets, and casters. Volume lines to fill the air: work gloves, safety helmets and empty tool cases. A pallet of casters and two pallets of gloves in the same box is not an accident — it is the mix that makes the freight arithmetic work.
Two practical fill notes. Floor-loading cartons almost always beats palletising for tools, because pallets waste 10–15 % of the cube; if the destination cannot handle floor-loaded cartons, palletise only what needs it. And load heavy cartons at the bottom and toward the centre, with lighter goods against the walls, which also reduces condensation damage on the light items.
7. Landed cost, the number to decide on
Compare orders on landed cost per unit, not FOB price: goods value plus freight plus insurance plus duty plus inland delivery, divided by sellable units. A 3 % higher FOB price on goods that fill a container better can be a lower landed cost, and a 5 % cheaper price on an order that needs a second container is not cheaper at all. Keep the calculation in the same spreadsheet as the MOQ figures — they interact.
Mixed orders and container fill — questions buyers ask
How much fits in a 40 ft high cube?
About 76 m³ of volume and roughly 26 tonnes of payload, plus 20–21 EUR pallets single tier. Which limit you hit depends on the goods: steel tools will reach the weight limit at around half the volume, gloves and helmets will fill the cube at a fraction of the weight.
Is a 40 ft always cheaper per unit than a 20 ft?
Per cubic metre, usually yes. Per tonne, not necessarily — the 40 ft carries less payload than a 20 ft because the box itself is heavier. If your order is dense steel, compare a 20 ft plus LCL for the light items against a single 40 ft before assuming bigger is cheaper.
How do I get a lower MOQ without paying more per unit?
Change what the MOQ is protecting. Ask for the price with a plain carton instead of a printed one, with a standard colour instead of a custom one, and with the order measured per order rather than per item. Each of those removes a set-up cost, and each usually moves the MOQ down.
How far ahead should I place an order that lands after Chinese New Year?
At least 90 days before the holiday for catalogue items, longer for anything with tooling. Factories close for two to four weeks and ramp up slowly; an order placed six weeks before the shutdown typically ships six weeks after it, which is the point at which buyers start paying air freight.
Should I inspect before shipment or on arrival?
Before shipment, always. A pre-shipment inspection at a defined AQL catches the lot while the supplier still has to fix it, and it is a fraction of the cost of a claim after the vessel has sailed. Arrival inspection is for confirming that what was inspected is what was loaded.
Send the article list with quantities and destination port. We will come back with the carton volume and weight per line, the MOQ position per item, and a fill plan that shows whether you are weight-limited or volume-limited before you commit.